Project detail

23 March 2020

LAMDA

Facilities include:
• 200 – seat theatre
• 80 – seat practice theatre
• 12 150m2 dance and rehearsal studios
• TV studios and radio suite
• 12 music practice rooms and meeting rooms and co-working space
• Fully acoustic rated spaces to lowest achievable level

Programme Length:
• Pre Contract: 4 Months
• Post Contract Mobilisation And Construction: 27 Months

Notes:
• Restricted Site, Landlocked On Three Sides
• London’s Busiest Road (A4 Talgarth Road)
• TFL Tube Network (Piccadilly & District Line)

Interesting Facts:
• 26 Miles Of SLAV Cabling
• 4 Million Tons Of Steel
• Enough Acoustic Panelling To Cover Wembley Stadium

Client:
• Benedict Cumberbatch (Board Chair)
• Joanna Reed (Principal)
• David Suchet (Board)
• Timothy West (Board Chair)

Team Members:
• Niall McLaughlin Architects
• VolkerFitzpatrick
• Charcoalblue
• Gillieron Scott
• Pell Frischmann