3 June 2026
03-06-2026 Les Ozouets Campus Update
The latest update from Les Ozouets Campus shows a project that is firmly in its stride. One key milestone worth calling out this week is the completion of lightning protection on the PAC Building, with certification now issued.
Sign-off and certification on a system like that is a meaningful step in the journey toward a building being ready for occupation.
On the main building, windows are now being installed across levels 1 and 2 on the North Elevation, with reveals in place from ground to level 2. External boarding and sealing is ongoing across all floors, the final roof coating continues at level 3, and fire stopping sample walls are being erected. Concrete plinths for plant equipment are in, and the parapet frame installation at level 3 continues.
In the Construction Building, the level 1 mezzanine deck is complete with roof level works ongoing, concrete pours are progressing to dwarf walls and the first section of level 1, and rebar installation is advancing across the remainder of the floor plate. Sika waterproofing continues at lower level perimeter.
Externally, retaining walls to both the east and west sides of the Construction Building are being prepared for shuttering and pour, with sprinkler sub-base and roadway works continuing across the site.
Another solid week at a project that is building real momentum toward completion. BAQUS continues in its role as NEC Supervisor for the State of Guernsey.