05-11-26 | Les Ozouets Campus Project Update

Progress continues at Les Ozouets, with works advancing across the Main Building, PAC Building, Construction Building and external areas.

Within the Main Building, the final section of parapet adjacent to the PAC Building is complete, while external wall cladding continues along the south elevation. Internal decorations and partition jointing are progressing across all levels, alongside ongoing mechanical and electrical first-fix installations, MVHR ductwork and insulation. Plantroom installations and passive fire protection works continue, with initial areas ready for review and sign-off. Raised access flooring, floor boxes, lift installations and sprinkler pipework are also progressing, while the final section of roofing works has commenced.

At the PAC Building, the final sections of removal works have been undertaken, while a section of the PAC car park has been handed back for use.

The Construction Building is also progressing, with final Kalzip roof cladding installations underway across the saw-tooth roof sections. Fire protection boarding is nearing completion on the ground and first floors, alongside ongoing sprinkler pipework and SFS framework installations. Internal partition works continue, while the first areas of mist coating have commenced and window installations progress on the first floor.

Externally, paving works continue across the main car park, alongside preparations for the next section of retaining wall near the Motorcycle Bay. Grading and levelling works are progressing in the rear meadow, while electrical cabling works continue, with final terminations completed. Preparations for the new drainage tank are underway, alongside roofing works to the external store and formation of a new concrete trench for incoming cables.

BAQUS is pleased to continue supporting the coordinated delivery of the Les Ozouets project as construction progresses across the site.