10 November 2025

Les Ozouets Campus – November Update

Progress continues at pace across site 👷‍♂️ At our ongoing project, major milestones have been reached this month: binding pads for the main building are now complete, with works progressing across Zones 1A–1C and the PAC area.

Insulation and Sika waterproofing have commenced in the construction building, while drainage works and duct installations continue following recent design updates.

Lift shafts 1 and 2 are also advancing well—with formwork, steel rebar, and pours progressing through levels 1 and 2. A temporary access road has been installed to support site logistics, and ongoing concrete and stone grading works are shaping the next phase of development.

A great effort by all teams on site as this complex build moves forward.

Andy Welch – Director at BAQUS  “Excellent progress and coordination across the site. Always great to see milestones like this being achieved through strong teamwork and planning. 👏 “